Magistrate's Court Flushing Project
Problem
How to complete a system flush on a building whilst the building needs to remain online and functioning.
Client
Amey
Services
Closed System Chemical Cleaning Services >>
Solution
Kirkee successfully completed a complex flushing project at the Bristol Magistrates' Court, where maintaining operational continuity was critical to avoid substantial fines. The project involved flushing both heating and chilled water systems, while ensuring the building remained fully functional throughout the process.
We handled the removal of waste glycol and obtained the necessary discharge notice from the local water authority for the flushing activities.
Balancing the flushing process while keeping the building online required planning and execution. Our team of experts employed ensured the project was completed efficiently and without disrupting the court's operations.
This project demonstrates Kirkee 's ability to deliver critical infrastructure services in complex and demanding environments. Our commitment to minimising disruption and ensuring compliance with regulatory requirements is evident in our successful completion of this project.